The order of renovation work, room by room

Work from the structure out to the finish: structural and layout changes first, then first-fix electrics and plumbing, then plastering and drying, then floors, joinery and second fix, and decoration last. Each trade finishes before the next starts on top of it, so nothing finished is damaged by the work that follows.

Updated 2 min readBy the Solubius team

Many renovation problems come from work done in the wrong order: a floor laid before the plastering, a fitted cupboard built against a wall that later moves, a room painted before the electrician has been back. That usually happens when trades are booked one at a time.

We plan renovations in the order below. It is a general sequence, and every house adjusts it.

1. Survey, scope and approvals

Before anything is booked: what the house needs, what is structural, what needs planning permission or Building Regulations approval, and what is out of scope. The answers go into a written scope, with the order of the work. Structural work and anything needing approval is designed and approved first, because everything else depends on it.

2. Strip out and repair

Old fittings, damaged plaster and failed finishes come out. Cracks are raked out and filled, loose plaster is cut back, and anything that would undermine the finish, such as damp, is found now rather than after decorating.

3. Layout and first fix

New non-load-bearing partitions go up, door openings are formed, and the first fix happens: the cables, pipes and back boxes that will be hidden inside walls, floors and ceilings. The consumer guide Which? describes first-fix carpentry, plumbing and electrics as the stage before plastering.

4. Plastering, then drying

Walls and ceilings are boarded and skimmed. New plaster has to dry before it is decorated. How long depends on the thickness, the temperature and the ventilation, so we check it rather than go by the calendar. Which? puts drying at about a week before second fix.

5. Floors, joinery and second fix

Once the wet and dusty work is done, the finished floors go down and the skirting goes on. Fitted joinery is built to the finished walls and floor, so it sits tight against them. The electrician and plumber come back to do the second fix: sockets, switches, lights, radiators and taps.

6. Decoration

New plaster is sealed with a diluted first coat (a mist coat) so the finish coats bond. Then the rooms are painted. Decoration goes last because it is the easiest thing to damage.

7. Snagging and handover

Every room is checked against the scope, small faults are put right, and the house is cleaned and handed back.

Lived in or empty

In an empty house, the whole sequence can run through every room at once. In a lived-in home, we plan it room by room. You always have somewhere to live while the rest is done, and floors and furniture are protected before each stage starts.